Citicore Seeks ERC Nod for ₱37.2-M Transmission Line Linking 75-MW Bolbok 2 Solar to Luzon Grid
Citicore Powers Luzon Grid Expansion with Bolbok 2 Solar Transmission Project
Citicore Solar Batangas 2, Inc. (CSBat2I) is taking giant leaps towards consolidating renewable energy infrastructure in the Philippines. The firm recently filed an application with the Energy Regulatory Commission (ERC) to allow the development and ownership of a stand-alone transmission line connecting its 75-megawatt (MW) Bolbok 2 Solar Power Project to the Luzon power grid. Such a PHP 37.2-million investment is yet another ambitious move toward a greener and more robust energy future for the nation.
Interconnecting Solar Power to the Grid
The planned transmission line is a key element in making sure clean energy from the Bolbok 2 Solar plant finds its way to Luzon consumers. The point-to-point line will run from the solar farm, which is situated in Barangay Bolbok, Tuy, Batangas, to the National Grid Corporation of the Philippines’ (NGCP) 69-kilovolt Tuy Substation.
Citicore underscored that the route was picked for its technical feasibility and least environment harm. The scheme will be entirely funded by CSBat2I, proving the company’s dedication to sustainable and autonomous growth.
Regulatory Progress
In a formal order of June 25, 2025, the ERC recognized that Citicore’s application was in the required form. As part of the regulatory process, a virtual hearing has been set on August 7, 2025, to consider the merits of the application and offer a forum for public participation.
CSBat2I is also applying for provisional authority from the ERC, something that would enable the company to start building the transmission line pending the full regulatory go-ahead. This is important in seeing the timely completion and commissioning of the Bolbok 2 Solar project.
Government Endorsements and Approvals
Citicore has already received a string of key government approvals and clearances that place the project on the success path:
- Certificate of Endorsement for Point-to-Point (COE-P2P) issued by the Department of Energy (DOE)
- Certificate of Energy Project of National Significance (CEPNS) – a certification awarded to high-impact energy projects
- Award under the Green Energy Auction Program 2 (GEA-2), a program designed to speed up renewable energy deployment in the Philippines
- Environmental Compliance Certificate (ECC) issued by the Department of Environment and Natural Resources (DENR)
- Certificate of Non-Overlap from the National Commission on Indigenous Peoples (NCIP), attesting that the project will not impact indigenous lands
- These clearances demonstrate the alignment of the project with national energy interests and adherence to environmental and social safeguards.
Influence on the Philippine Energy Scene
The Bolbok 2 Solar Power Project and its exclusive transmission line are poised to be an important contributor to the diversification of the Philippines’ energy mix. With a combined capacity of 75 MW, the solar farm will make a substantial contribution to Luzon’s power supply, helping to diminish the dependence on fossil fuels and contribute to the clean energy shift of the country.
The incorporation of renewable energy into the national grid is not merely a technological initiative; it’s a strategic initiative that is good for the environment and the economy. Initiatives such as Bolbok 2 illustrate how the private sector can take the lead in developing sustainable energy solutions while promoting job creation and economic activity in host communities.
Next Steps and Community Engagement
As directed by ERC directives, CSBat2I is now actively pursuing fulfillment of public consultation obligations. This involves informing affected communities, posting notices of the upcoming hearing, and holding coordination with concerned government offices like the NGCP.
Local stakeholder engagement is a must for the seamless rollout of infrastructure projects. Citicore’s pro-active information drive and transparency campaign are designed to elicit support from the people and ensure community issues are brought up throughout the life cycle of the project.
Conclusion:
Citicore’s proposed PHP 37.2-million transmission line linking the Bolbok 2 Solar Power Project to the Luzon grid is a milestone in Philippine renewable energy. With robust regulatory compliance, financial investment, and vision for sustainable development underpinning it, the project is a testament to the nation’s transition towards cleaner, more consistent sources of power.
With all significant endorsements secured and the regulatory process actively underway, CSBat2I is poised to implement a project that not only lights up homes and enterprises but also shines the way to a sustainable future.
FAQs
Q1: What is the Bolbok 2 Solar Power Project?
Bolbok 2 Solar Power Project is a 75-megawatt solar power plant built by
Citicore Solar Batangas 2, Inc. (CSBat2I) in Barangay Bolbok, Tuy, Batangas.
It will provide clean and renewable power to the Luzon
grid.
Q2: What is the transmission line for?
The transmission line will be directly linked to the NGCP’s
Tuy Substation from the Bolbok 2 solar plant. This way, the power produced can
be efficiently distributed via the Luzon grid.
Q3: Who is funding the project?
The whole PHP 37.2-million cost of the transmission line will
be covered by CSBat2I, without any added financial undertaking on
the part of the government.
Q4: Has the project received government approval?
Yes. The project has obtained different critical permits such as the
DOE’s COE-P2P, a CEPNS, an ECC from the DENR, and a Certificate of Non-Overlap
from the NCIP.
Q5: When can the project break ground?
Construction will start once the ERC gives provisional
authority. The issue is up for hearing on August
7, 2025.
Q6: How will the community be engaged?
CSBat2I has been mandated to alert neighboring communities
and engage them in public consultations. The intention is
to make the process transparent and obtain views from
all stakeholders.